The project
A new 12,000 sq ft commercial facility in San Juan Capistrano needed a full post-construction clean before handover: offices, break rooms, locker rooms, restrooms, corridors, an elevator and the exterior. Construction and installation crews were still working in the building, so our team of seven followed the site's safety rules and the client's requirements the whole time, with hi-vis vests, marked wet floors and work scheduled around the other trades.
How we phased it
- Residue removal — paint drips, silicone, tape and adhesive taken off glass, frames, counters, fixtures and floors.
- Protective film — film peeled from metal surfaces, including the elevator interior and the restroom and utility sink fixtures.
- High windows and hard-to-reach areas — high windows inside and outside, ledges, frames and spots that needed ladders or lifts.
- Rooms and floors — cabinets, restrooms, locker rooms and offices detailed, then polished concrete and resilient floors cleaned as the last step.
Challenges
Cleaning a building that is still being finished means working around lifts, ladders and other crews, and keeping every area safe for everyone on site. The size of the job and the amount of residue left by the trades took steady, coordinated work from all seven cleaners over four days.
Result
The facility was handed over with clear glass inside and out, residue-free surfaces, film-free metal fixtures and clean floors throughout.